Customer:
Kier Infrastructure & Overseas Ltd
CONTRACT:
Kings Cross Station
EQUIPMENT:
Tube & Fittings
DESIGN BRIEF:
NORTH FACADE ACCESS: To provide drawings, calculations and Form C document, for internal and external access to the north facade. Scaffold encapsulated at RIB level 39, with internal and external scaffolds tied together with raker buttressing. Design load 1.50kN/m² – 2.00kN/m²
CENTRAL VALLEY: To provide drawings, calculations and Form C document for a temporary roof to cover the central valley and allow for removal and installation of gutter and lower barrel roof works. Supported from end walkway brackets.